Challenger
Home
Exams
Lab Assistant
University Assistant (Prelims)
High Court Assistant
Degree Mains
University LGS
LDC 2024
Degree Prelims 2024
Khadi Board LDC
Civil Excise Officer
LSGS
Questions
Notes
Blog
Contact Us
e-Book
×
Home
Exams
Lab Assistant
University Assistant (Prelims)
High Court Assistant
Degree Mains
University LGS
LDC 2024
Degree Prelims 2024
Khadi Board LDC
Civil Excise Officer
LSGS
Questions
Notes
Blog
Contact Us
e-Book
☰
Home
Questions
Maths
Time & Work
Question:
Thirty men can complete a work in 36 days. In how many days can 18 men complete the same piece of work?
A
48
B
36
C
60
D
72
Answer:
C. 60
Explanation:
Required number of days = (30 * 36)/18= 60
Related Questions:
A work could be completed in 22 days. However due to three workers being absent, it was completed in 24 days. The original number of workers was.
A can do a work in 12 days. When he had worked for 3 days, B joined him. If they complete the work in 3 more days, in how many days can B alone finish the work?
A യും B യും ചേർന്ന് 20 ദിവസം കൊണ്ട് ഒരു പ്രവൃത്തി ചെയ്യാൻ കഴിയും. അവർ ഒരുമിച്ച് പ്രവൃത്തി ആരംഭിക്കുന്നു, പക്ഷേ പ്രവൃത്തി പൂർത്തിയാകുന്നതിന് 5 ദിവസം മുമ്പ് A യ്ക്ക് വിട്ടുപോകേണ്ടി വരുന്നു. ബാക്കിയുള്ള പ്രവൃത്തി 18 ദിവസം കൊണ്ട് പൂർത്തിയാക്കാൻ B യ്ക്ക് കഴിയുമെങ്കിൽ, B ഒറ്റയ്ക്ക് എത്ര ദിവസം കൊണ്ട് മുഴുവൻ പ്രവൃത്തിയും പൂർത്തിയാക്കും?
24 people can finish a job by 10 days. How many days will be required to finish the same job by 8 people?
ജോണും ദീപുവും ചേർന്ന് ഒരു ജോലി ചെയ്തു തീർക്കാൻ 45 ദിവസം എടുക്കുന്നു.എന്നാൽ ജോൺ ഒറ്റയ്ക്ക് ഈ ജോലി 70 ദിവസം കൊണ്ട് ചെയ്തു തീർക്കും. ദീപു ഒറ്റയ്ക്ക്ഇതേ ജോലി ചെയ്തു തീർക്കാൻ എത്ര ദിവസം എടുക്കും?